On September 1, 2026, representatives from EDL-Generation Public Company (EDL-Gen) attended the official handover meeting for the 22 kilovolt (kV) medium voltage distribution line construction project along Route 516, covering a distance of 5.9 kilometers in Longxan District, Xaysomboun Province. The meeting was held at Nam Leuk Hydropower Plant, Longxan District, Xaysomboun Province.The completion and official handover of this project play a crucial role in enhancing the efficiency and stability of power distribution to ensure a sufficient electricity supply for the local population. Furthermore, it contributes to overall economic development and continuously improves the livelihoods of the people in Longxan District, Xaysomboun Province